Construction progress: July 2026
Monthly site report: monolithic works of Building 1 reached the 9th floor.
Our monthly progress report. In July construction is two weeks ahead of schedule.
Highlights of the month
Building 1: the monolithic frame is complete up to the 9th floor, external wall masonry started on the lower floors. Building 2: the foundation slab is finished.

- Building 1 — 9th floor frame, masonry on floors 1–3.
- Building 2 — foundation slab 100% complete.
- Utilities — external water supply line finished.
A pace of two floors per month lets us confidently confirm the announced completion date.
Chief project engineer