Foundation works of the first phase are complete
Foundations of both first-phase sections are ready — moving on to the above-ground part.
A key project milestone: the ground cycle of the first phase is fully complete and accepted by technical supervision without remarks.
How the foundation is built
The foundation is a monolithic slab on piles up to 18 metres deep. The structure has a strength reserve and fully meets the regional seismic codes.

- Piles — 640 pcs, up to 18 m deep.
- Slab — 1.2 m, C30/37 concrete.
- Waterproofing — two-layer torch-on.
The ground cycle is the most critical stage. From here the construction pace doubles.
Technical director
The photo report from the site is updated weekly in the Construction progress section.